Generation
Los Guindos I & II (Chile)
278 MW open-cycle. Planned expansion to 420 MW combined-cycle.Bolivian Hydroelectric
Design, supply and execution of the complete electrical system.Uyuni Solar Plant (Bolivia)
Connection to the system and start of operation.





![DSC02499[29].JPG](https://static.wixstatic.com/media/9c4166_7db2a27d85de41c292d21d324fa6ec7f~mv2.jpg/v1/fill/w_245,h_184,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/9c4166_7db2a27d85de41c292d21d324fa6ec7f~mv2.jpg)
Generation
LT Sucre – Punutuma – San Cristóbal (Bolivia)
230 kV line with comprehensive operation and maintenance.LT Punutuma – Uyuni – Lithium (Bolivia)
Key infrastructure for lithium development.LT Belo Monte – XRTE (Brazil)
+430 km of 800 kV HVDC | Tower manufacturing and supply.LT Minera Teck (Chile)
Project for the energy supply of mining operations.


![DSCF7761[33].jpg](https://static.wixstatic.com/media/9c4166_dcfbc33b38b045119a014082ebe7dbe2~mv2.jpg/v1/fill/w_164,h_123,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/9c4166_dcfbc33b38b045119a014082ebe7dbe2~mv2.jpg)






Generation
Los Guindos I & II (Chile)
278 MW open-cycle. Planned expansion to 420 MW combined-cycle.Bolivian Hydroelectric
Design, supply and execution of the complete electrical system.Uyuni Solar Plant (Bolivia)
Connection to the system and start of operation.





EPC
Warnes, Uyuni and San Cristóbal Substations (Bolivia)
Engineering, assembly, testing and commissioning.Pascua Lama – Veladero System (Chile/Argentina)
Substations at 4,000+ meters above sea level, wind farm and binational line.Electrical system for Collahuasi Mining (Chile)
Design and construction of 7 substations and 1 transmission line for one of the country's main mining operations.Punta Colorada Wind Farm (Chile)
10 wind turbines | Complete electrical works.